Seller was motivated to sell quickly and thus the property was acquired at a competitive price.
Schedule of works included:
Seller was a tired landlord and wanted to cash in and move on. We were able to secure it at a price that suited.
The property was refurbished completely internally
Seller was motivated due to financial difficulties. We were able to secure it at a price that helped both parties.
The property was refurbished completely internally
This project took 6 months from start to finish and is being marketed for rent right this moment.
Seller was motivated due to financial difficulties. We were able to secure it at a price that helped both parties.
The property was refurbished completely internally
This project took 6 months from start to finish and was successfully let on completion immediately, achieving a rental of £3150pcm gross.
Auction purchase. Reconfiguration of 1bed to 2bed property combined with a lease extension.
The property was refurbished completely internally
The project was completed within 3 months of acquisition and the property was retained for long term capital growth as part of the diversification of the portfolio.
Refurbishment of a property acquired for a client.
The property was refurbished completely internally
The project was completed within 3 months of acquisition and the investor made a profit of £40,000.
A conversion of a 3 bedroom, one bathroom maisonette to a luxury 4bed, 3bath duplex aimed at the professional sharer market.
Briefly we tranformed this property by:
The project was completed within 4 months and allowed us to refinance the property, recouping much of the initial investment and allowing us to hold the property for our portfolio.
A lot of love went into this project. This was a run-down 4 bedroom maisonette. After the transformation we ended up with a 5 bedroom, 3 bathroom luxury accomodation and successfully secured good tenants within 3 days of completion of the works!
Briefly we tranformed this property by:
The project was completed within 4 months and allowed us to refinance the property, recouping much of the initial investment and allowing us to hold the property for our portfolio.
This particular project was a straightforward refurbishment of an otherwise solid apartment. The property had been neglected over the years so the programme of works included:
The project was completed within 2 months and allowed the investor to let out the property to refinance, recouping half of their investment and hold the property for their long term hold and rent portfolio.
The initial outlay (including deposits, legal fees and refurbishment costs) was £110,000 and the investor was able to refinance £55,000 back out of the property due to the increase in value as well as retain a healthy cash flow of nearly £1000pcm.
This property was very unloved by its previous owners. The property was acquired at auction and problems were taken care of. A treatment plan was put in place for the knotweed, communal areas were redecorated, gardens were tended to as well as:
The project was complete within 2 months and the property was sold on the open day, allowing a healthy return for the investors.
The initial outlay (including deposits, legal fees and refurbishment costs) was £75,000 and the property was sold to return a healthy return of over 40% on money invested. The project was turned around in less than 6 months.